Primary Electrical Distribution Replacement at the Geelong Refinery
The project scope was to construct a new Main Incoming Substation (MIS), install & Cut Over three new HV switchboards to replace: –
- 1x 22kV Distribution switchboard(s)
- 1x 6.6kV Distribution switchboard
- 1x 6.6kV Plant switchboard
These three switchboards form the heart of the Refinery’s Electrical Distribution network, and are critical to the safe operation of the entire Refinery.
The Cut-Over and Commissioning phase was implemented with no planned interruption to electrical supply, with the electrical circuits being ‘cutover’ seamlessly to Refinery electrical operations: –
The PEDR project was implemented in a phased approach:
Phase 1: Demolition & Construction of new Main Incoming Substation (MIS) – Complete
Phase 2: Procurement & Installation of new switchboards, 6.6kV Cut Overs – Complete
Phases:-
2a) Substation Fit-out (Initial and Final Stages) – Complete
2b) Cable, Trenching and Miscellaneous Installations – Complete
2c) Distribution Switchboard Cut-overs – Complete
2d) Plant Switchboard Cut-overs – Complete
(10xFeeders, 4xTransformers, 2xTurbines, 6xMotors)
Phase 3: 22kV Cut Overs
Phases:
3a) 22kV Equipment and Cable Installation –
3b) 22kV Cut-Overs
Interested in learning more? Get in contact with our highly trained Frontline Electrical team today on (03) 6228 1022.